东京热加勒比天然素人无码-东京热加勒比无码精品91热-东京热加勒比无码少妇-东京热加勒比无码视频-东京热精品-东京热精品97综合网

歡迎來到濱州恒通電力器材有限公司網站,我們竭誠為您服務

公司新聞
當前位置:首頁-資訊中心>公司新聞燃氣管道警示帶的三個埋設要點

燃氣管道警示帶的三個埋設要點

來源:http://www.tjshouche.cn/ 發布時間:日期:2023-02-04 0
1.溝槽開挖。
1. Trench excavation.
(1)混凝土路面和瀝青路面的開挖應使用切割機切割。
(1) The excavation of concrete pavement and asphalt pavement shall be cut by cutting machine.
(2)管道溝槽應按設計規定的平面位置和標高開挖。當采用人工開挖且無地下水時,槽底預留值應為0.05~0.10m;管道安裝前應人工清底設計標高。
(2) The pipe trench shall be excavated according to the plane position and elevation specified in the design. When manual excavation is adopted and there is no underground water, the reserved value at the bottom of the trench shall be 0.05~0.10m; Before pipeline installation, the bottom shall be cleaned manually to the design elevation.
(3)管溝溝底寬度和工作尺寸,應根據現場實際情況和管道敷設方法確定。
(3) The width and working size of the trench bottom shall be determined according to the actual situation on site and the pipeline laying method.
(4)局部超挖部分應回填夯實。當溝底無地下水時,超挖在0.15m以內,可采用原土回填;超挖在0.15,以上,可采用石灰土處理。當溝底有地下水或水量較大時,應采用級配砂石或天然砂回填標高。超挖部分回填后壓實,其密實度應接近原地基天然土的密實度。
(4) The partial overbreak shall be backfilled and compacted. When there is no groundwater at the bottom of the ditch, the over-excavation is within 0.15m, and the original soil can be used for backfilling; If the overbreak is more than 0.15, lime soil can be used for treatment. When there is groundwater at the bottom of the ditch or there is a large amount of water, graded sand or natural sand shall be used to backfill to the elevation. The over-excavated part shall be compacted after backfilling, and its compactness shall be close to the compactness of the original foundation natural soil.
(5)在濕陷性黃土地區,不宜在雨期施工,或在施工時切實排除溝內積水,開挖時應在溝底預留值0.03~0.06m厚的土層進行壓實處理。
(5) In the collapsible loess area, construction should not be carried out in rainy season, or the accumulated water in the ditch should be effectively drained during construction. During excavation, a soil layer with a thickness of 0.03-0.06m should be reserved at the bottom of the ditch for compaction.
(6)溝底遇有廢棄構筑物、硬石、木頭、垃圾等雜物時須,并應鋪一層厚度不小于0.15m砂土或素土,整平壓實及設計標高。
(6) In case of waste structures, hard rocks, wood, garbage and other sundries at the bottom of the ditch, they must be removed, and a layer of sand or plain soil with a thickness of not less than 0.15 m should be paved, leveled and compacted to the design elevation.
(7)對軟土基及特殊腐蝕土壤,應按設計要求處理。
(7) Soft soil foundation and special corrosive soil shall be treated according to design requirements.
管道警示帶
2.回填土。
2. Backfill.
(1)不得采用凍土、垃圾、木材及軟性物質回填。管道兩側及管頂以上0.5m內的回填土,不得含有碎石、磚塊等雜物,且不得采用灰土回填。距管頂0.5m以上的回填土中的石塊不得多于10%、直徑不得大于0.1m,且均勻分布。
(1) Frozen soil, garbage, wood and soft materials shall not be used for backfilling. The backfill on both sides of the pipe and within 0.5m above the pipe top shall not contain debris such as gravel and bricks, and shall not be backfilled with lime soil. The stones in the backfill soil more than 0.5m from the pipe top shall not be more than 10%, and the diameter shall not be more than 0.1m, and shall be evenly distributed.
(2)溝槽的支撐應在管道兩側及管頂以上0.5m回填完畢并壓實后,在保證的情況下進行拆除,并應采取細砂填實縫隙。
(2) The support of the trench shall be removed under the condition of ensuring safety after backfilling and compaction on both sides of the pipe and 0.5m above the pipe top, and the gap shall be filled with fine sand.
(3.)溝槽回填時,應先回填管底懸空部位,再回填管道兩側。
(3) When backfilling the trench, the suspended part of the pipe bottom shall be backfilled first, and then both sides of the pipe shall be backfilled.
(4)回填土應分層壓實,每層虛鋪厚度宜為0.2~0.3m,管道兩側及管頂以上0.5m內的回填土須采用人工壓實,管頂0.5m以上的回填土可采用小型機械壓實,每層虛鋪厚度宜為0.25~0.4m。
(4) Backfill soil shall be compacted by layers. The virtual paving thickness of each layer should be 0.2~0.3m. Backfill soil on both sides of the pipeline and within 0.5m above the pipe top must be compacted manually. Backfill soil above 0.5m above the pipe top can be compacted by small machinery. The virtual paving thickness of each layer should be 0.25~0.4m.
(5)回填土壓實后,應分層檢查密實度,并做好回填記錄。
(5) After the backfill is compacted, the compactness shall be checked layer by layer and the backfill records shall be made.
3.警示帶鋪設。
3. Laying of warning tape.
(1)埋設燃氣管道的沿線應連續鋪設警示帶。警示帶鋪設前應將鋪設面壓實,并平整的鋪設在管道的正上方,距管定的距離宜為0.3~0.5m,但不得鋪設于路基和路面內。
(1) Warning tapes shall be laid continuously along the buried gas pipeline. Before laying the warning tape, the paving surface should be compacted and laid flat above the pipe. The distance from the pipe should be 0.3~0.5m, but it should not be laid in the roadbed and pavement.
(2)警示帶宜采用黃色聚乙烯等不易分解的材料,并印有明顯、牢固的警示語,字體不應小于100*100mm。
(2) The warning tape should be made of yellow polyethylene and other materials that are not easy to decompose, and should be printed with obvious and firm warning words. The font should not be less than 100 * 100mm.
現在的警示帶有示蹤線,利用測試儀器在不開挖的情況下,準確為管道定位。您有需求就來我們網站http://www.tjshouche.cn咨詢了解吧!
The current warning is equipped with a tracer line, which uses test instruments to accurately locate the pipeline without excavation. Come to our website if you need http://www.tjshouche.cn Ask about it!

相關產品 / Related products

  • 地釘

    地釘

  • 地釘

    地釘

  • 警示樁

    警示樁

  • 警示樁

    警示樁

截屏,微信識別二維碼

主站蜘蛛池模板: 91精品国产综合久久久久久 | 国产成人午夜视频影院免费观看 | 国产精品成人v?在线观看 | 2025国产麻豆剧传媒网站 | 国产精品一区二区制服丝袜 | 国产aⅴ一区 | 国产av国片精品麻豆 | 国产激情久久久久影 | 91在线无码一区二区 | 国产精品欧美一区 | 国产精品视频一区二区噜噜 | 国产古代三级在线播放 | 国产三级在线播放放视频 | 国产三级av在在线观看 | 国产微拍精品一区二区 | 2025最新国产三级在线看 | 91久久国产综合精品女同国语 | 国产精品不卡一区二区三区四区 | 成人一区在线观看 | 91精品酒店情 | 成人午夜亚洲精品无码区 | 99精品国产丝袜在线拍国语 | 99精品久久久久中 | 国产精品一区二区电影 | 国产福利不卡在线观看 | 成人青青热久免费精品 | 国产精品成人在线观看 | 国产一区二区三区高清在线观看 | 精品国产一区二区三区四区不 | 国产一区二区三区在线 | 国产av激情无码久久 | 国产精品宅男宅女 | 国产精品视频一区二区亚瑟品尚网 | 国产成人午夜福利在线观看 | 国产精品日韩欧美 | 国产成人自啪精品视频 | 国产精品黄黄久久久免 | 国产主播在线一区二区 | 91极品女神私人尤物在线播放 | 国产精品va在线观看老妇女 | 国产精品美女久久 |